Issue - meetings

Variation of Legal Agreement of 17/01511/FULM

Meeting: 03/07/2019 - Development Management Committee (Item 12)

12 Variation of Legal Agreement of 17/01511/FULM pdf icon PDF 373 KB

Variation of the S106 Agreement to fix the number and mix of dwellings in Phase 1 and allow for flexibility in the commencement for any unforeseen delays.

Minutes:

The committee received the report of the interim Head of Development Management, including the relevant planning history of the site and details of the responses to the application. 

 

The interim Head of Development Management introduced the item.  She explained that the application sought a variation of a section 106 agreement of the above planning application to fix the number and mix of dwellings in phase 1 and allow for flexibility in the commencement for any unforeseen delays.

 

In response to a question, the interim Head of Development Management confirmed that the variation would not affect the number or mix of affordable housing units for phase 1.

 

There were no speakers and the Chair moved the officer’s recommendation.

 

RESOLVED –

 

That the S106 associated with planning permission 17/01511/FULM be varied to:

 

1)         Allow flexibility for the commencement date; and

2)         Remove Phase 1 from the viability review regardless of the commencement date.