Issue - meetings

Issue - meetings

20/01491/FULM - Dhamecha, Imperial Way, Watford, WD24 4UA

Meeting: 14/04/2021 - Development Management Committee (Item 63)

63 20/01491/FULM - Dhamecha, Imperial Way, Watford, WD24 4UA pdf icon PDF 528 KB

Additional documents:

Minutes:

The committee received the report of the Principal Planning Officer (HH).

 

                   The Chair then asked the committee for any comments or questions.  There being none, he put the vote to the committee to approve the officer’s recommendation to approve the application that planning permission be granted, subject to the conditions and informatives listed in the report. 

 

                   In accordance with Standing Committee Procedure Rules, paragraph 4.2, the Chair requested that it be recorded in the minutes how members cast their votes.

 

                   Those members voting for the motion:

Councillors Bell, Collett, Jeffree, Johnson, Mills, Pattinson, Sharpe, Smith and Watkin

 

                   Those members voting against the motion:

                   None.

 

                   Those members abstaining:

None.

 

                   RESOLVED -

That planning permission be granted, subject to the conditions and informatives listed below:     

 

                   Conditions

 

1.      The development to which this permission relates shall be begun within a period of three years commencing on the date of this permission.

 

2.      The development hereby permitted shall be carried out in accordance with the following approved drawings:

 

         DWF-PL-500 – Proposed Ground Floor Plan and Proposed Roof Plan

         DWF-PL-500 – Proposed Elevations

         DWF-PL-401 – Block Plan Site Plan

         DWF-PL-400 – Site Location Plan

 

3.    No development approved by this planning permission shall commence until a remediation strategy to deal with the risks associated with contamination of the site has been submitted to, and approved in writing by, the Local Planning Authority. This strategy will include the following components:

 

1)          A preliminary risk assessment which has identified:

• All previous uses;

• Potential contaminants associated with those uses;

• A conceptual model of the site indicating sources, pathways and receptors; and

• Potentially unacceptable risks arising from contamination at the site.

 

2)  A site investigation scheme, based on (1) to provide information for a detailed assessment of the risk to all receptors that may be affected, including those off site. 

 

3)  The results of the site investigation and the detailed risk assessment referred to in (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken.

 

4)  A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in (3) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action.

 

Any changes to these components require the written consent of the local planning authority. The scheme shall be implemented as approved.

 

4.      No development shall commence until a monitoring and maintenance plan in respect of contamination, including a timetable of monitoring and submission of reports to the Local Planning Authority, has been submitted to, and approved in writing by, the Local Planning Authority. Reports as specified in the approved plan, including details of any necessary contingency action arising from the monitoring, shall be submitted to, and approved in writing by, the Local Planning Authority.

 

5.      No development shall commence until the final design of the drainage scheme has  ...  view the full minutes text for item 63


 