Issue - meetings
20/00121/VARM - 7-15 Bridle Path
Meeting: 03/06/2020 - Development Management Committee (Item 6)
6 20/00121/VARM - 7-15 Bridle Path PDF 392 KB
Additional documents:
Minutes:
The Chair introduced the item to the committee and invited the Development Management Team Leader to present his report.
The Chair thanked the Development Team Leader and, noting there were no speakers, invited any comments from the Committee. There were no comments, so the Chair then proposed a vote to approve the application in accordance with the officer’s recommendation.
In accordance with Standing Committee Procedure Rules, paragraph 4.2, Councillor Peter Jeffree requested that it be recorded in the minutes how Members cast their votes.
Those members voting for the motion:
Councillors Bell, Collett, Jeffree, Johnson, Mills, Pattinson, Sharpe, Smith and Watkin.
Those members voting against the motion:
None
The motion was declared to be CARRIED by nine to none with no abstentions.
RESOLVED –
That planning permission be granted subject to the completion of a legal agreement under s.106 of the Town and Country Planning Act 1990 to secure the planning obligations listed below and the following conditions:
Section 106 Heads of Terms
i) To secure the following works within the public highway, as shown in
principle on approved drawing no. 1321-GTA-ZZ-XX-PS-A-0001 Rev.
P04:
a) The closure of the existing access at the eastern end of the site and the reinstatement of the footpath within the public highway.
b) The closure of the existing access at the western end of the site and the reinstatement of the footpath within the public highway.
Conditions
1. The development hereby permitted shall be carried out in accordance
with the following approved drawings:-
1321-GTA-ZZ-XX-PS-0001_Rev P04
1321-GTA-00-PG-A-0002_Rev P01
1321-GTA-3Z-ZZ-GA-A-0001_Rev P05
1321-GTA-3Z-ZZ-GA-A-0002_Rev P04
1321-GTA-3Z-ZZ-GA-A-0003_Rev P04
1321-GTA-3Z-ZZ-GA-A-0004_Rev P04
1321-GTA-3Z-ZZ-GA-A-0005_Rev P04
1321-GTA-3Z-XX-GE-A-0001_Rev P04
1321-GTA-3Z-XX-GE-A-0002_Rev P02
1321-GTA-3Z-XX-GE-A-0003_Rev P04
2. The development shall be carried out in accordance with the following
external materials, window reveals and patterned brickwork, as
approved under application ref. 17/00295/DISCON, unless otherwise
agreed in writing by the Local Planning Authority:
Drawing nos. 4156/WD/220D, 221E, 222D, 240B, 241A, 242A, 460
Ground floor facing brick - Vandersanden Neo Magnolia
Upper floors facing brick - Hoskins Brick Ledbury
3. The foundations of the development shall only be constructed utilising flight auger piling, in accordance with the following details approved under ref. 17/00295/DISCON, unless otherwise agreed in writing by the
Local Planning Authority:
24761_T_DRAFT - Topographical Survey
14414-10 T2 - Piling Layout
14116:SK02 - Sewer and Pile Location Plan
4. If, during development, contamination not previously identified is found to be present at the site then no further development shall be carried out until the developer has submitted to, and obtained written approval from, the Local Planning Authority for a remediation strategy detailing how this unsuspected contamination is to be dealt with. All works shall be carried out in accordance with the approved details.
5. The development shall only be carried out in accordance with the surface water drainage scheme, as approved under ref. 17/00295/DISCON, unless otherwise agreed in writing by the Local Planning Authority:
Drawing nos. 14116:101 T2, 102 T1, 103 T1, 104 T1
Drainage Maintenance Plan dated 02 June 2017 (ref. DS/14116) by
Simpson Consulting Engineers.