Financial Planning

Meeting: 14/01/2020 - Finance Scrutiny Committee (Item 21)

21 Financial Planning pdf icon PDF 496 KB

Report of the Head of Finance to enable the committee to consider service level expenditure, funding and council tax levels for the medium term 2020/21 to 2022/23.

 

 

 

 

 

 

Additional documents:

Minutes:

The committee received a report of the Head of Finance containing the service level expenditure, funding and council tax levels for the medium term 2020/21 to 2022/2023, including the use of reserves and the 2020/21 council tax calculations.

 

The Head of Finance introduced the report highlighting the key points. This included an anticipated additional 1% pay award, savings made in the insurance retender, the introduction of charging for the collection of green waste, borrowing costs related to changes in the capital programme and the impact of funding changes.

 

Members sought reassurance about the level of borrowing required to participate in the joint venture with Kier for the construction of the new multi-storey car park for the hospital. It was confirmed that the council would decide whether to lend into the scheme; if not it would provide £3.6 million in equity and would receive an income going forward. A car park operator would be sought to run it.

 

It was noted that the current approved capital programme included £750,000 for Watford Market and committee members asked how this would be spent and the impact the expenditure would have on the market. Officers reported that new gazebos had been purchased and investments had been made in the electrics and lighting. New proposals would be forthcoming to include a programme of activities. The outdoor food stalls were very popular and occupation levels were good. It was agreed that the Group Head of Community and Environmental Services would circulate the market occupancy levels to members.

 

The committee noted that the council would shortly hear the outcome of the application to the LEP for £5 million for a transport hub at the pyramid site. This would include a number of covered bus stops and electric car charging facilities; it would complement the highway works that had recently taken place in the area.

 

A question was raised about the anticipated budget gap over the next three years and how it was accounted for. The Head of Finance highlighted the salary increases and the temporary levelling off of rental income from Watford Business Park due to the redevelopment of the site. In response to further queries about the budget gap and the re-phasing of projects; officers noted that savings from the Watford 2020 project would be realised later in the MTFS and the associated risks were relatively low.

 

Members discussed the ongoing work in Oxhey Park; it was noted that additional work had been required by the Environment Agency and that the project was making good progress. The new BMX and skate park would open before the old site at Derby Road closed; with the aim of this being before the school summer holidays.

 

Following a query about the transport app, it was explained that this would be a Watford-focused mobile app. It would assist residents in making use of the public transport options available to them, including the demand responsive transport and the cycle scheme. More modes of transport would be added over time. There would  ...  view the full minutes text for item 21


 